Project
Location
Sector
Project Overview
132kV Substation Rehabilitation for Post-Conflict Power Restoration
Iraq
Energy
Our Solution
Supervised the installation and alignment of 33kV/11kV switchgear and power transformers across three critical substations.
Executed relay interfacing, bus bar setup, and complete grounding grid installation to ensure electrical safety and grid compliance.
Oversaw the installation of SCADA systems and control cabling to enable remote monitoring and automation.
Led the replacement and calibration of aging current transformers (CTs), and upgraded DC auxiliary systems using smart battery chargers and VRLA batteries.
Key Outcomes
Successfully restored stable and reliable electricity to multiple districts, directly supporting residential demand and critical facilities.
Modernized substation protection schemes with digitally configured relays and up-to-date grid compliance.
Delivered high-quality documentation and technical oversight in line with international standards, contributing to long-term infrastructure sustainability and grid resilience.